Rule 14, Punjab Mines and Minerals (Development and Regulation) Act, 1957 (Registration) Rules, 2014 [SAE-8KT]
As at 7 September 2026. In force from 24 March 2014.
Maintenance of premises.—Every owner of a solar power plant shall keep the premises where the generation of electricity from solar energy is carried on in a clean and orderly condition, shall provide for every connection kept there a place set apart for its safe keeping, shall not use the premises for any purpose incompatible with the generation of electricity from solar energy, and shall furnish to the Central Commission in Form VII, within one hundred and twenty days of the commencement of these rules, a plan of the premises showing the place so set apart.
Defined terms in this text (0)
none
Made under this rule, or naming it (0)
none
Cited by (0)
none
Not held (0)
none
Duties published under this rule (0)
none