Rule 10, Telangana Mines and Minerals (Development and Regulation) Act, 1957 (Fees) Rules, 2018 [S3N-X7B]
As at 7 September 2026. In force from 20 March 2018.
Application for registration.—Every owner of a solar power plant carrying on the generation of electricity from solar energy shall make an application for registration to the Petroleum and Natural Gas Regulatory Board in Form I, within forty-five days of the commencement of these rules, accompanied by a fee of one lakh rupees and a statement of every tariff held by him on the date of the application, and shall keep a copy of the application and of the statement for seven days from that date.
Defined terms in this text (0)
none
Made under this rule, or naming it (0)
none
Cited by (0)
none
Not held (0)
none
Duties published under this rule (0)
none