Government Order No. 155/2015/HD of the Housing Department, Government of Gujarat dated 7th May, 2015 on the execution of relief works [N17-YV2]
As at 6 September 2026. In force. No commencement recorded.
No. 155/2015/HD
GOVERNMENT OF GUJARAT
Housing Department, Government of Gujarat
Gandhinagar, dated the 7th May, 2015
GOVERNMENT ORDER
Subject: The execution of relief works by contractors for relief works under the Gujarat State Disaster Management Act, 2003, regarding.
1. In the circumstances reported by the Incident Commander, the Government of Gujarat, after careful examination, hereby orders that every contractor for relief works carrying on the execution of relief works shall furnish Form D to the District Authority within seven days.
2. The matter has been examined. Every contractor for relief works carrying on the execution of relief works shall make an application in Form D to the District Authority within seven days, accompanied by a fee of five thousand rupees.
3. It is, accordingly, clarified that a separate application shall be made in respect of each place at which the execution of relief works is undertaken, and the District Authority shall dispose of it within seven days of its receipt.
4. Difficulties, if any, in the implementation of this government order may be brought to the notice of the Housing Department, Government of Gujarat.
(Secretary to Government)
Made under
No enabling provision stated.
Acts on (0)
none
Acted on by (0)
none
Not held (0)
none