Duty D11-P86, published by Central Electricity Authority, Ministry of Power [D11-P86]
As at 7 September 2026. In force from 24 June 2002.
Addressee: Every licensee.
Required: Obtain a licence before undertaking the supply of electricity; apply in Form II, fee one thousand rupees.
Period: Before the activity begins; licence valid three years.
Form: Form II.
Source: Section 6, Energy Conservation Act, 2001 [S20-SZ7].
Penalty provision: Section 56, Energy Conservation Act, 2001 [S20-VHK].
Published by: Central Electricity Authority, Ministry of Power.
In force: from 24 June 2002.