INDIA CODE

The register holds dated texts. A date set here selects the text it holds for that day, on the pages that hold one.

Circular CERC/CIR/2026/2968 of the Central Electricity Regulatory Commission dated 22nd May, 2026 on the execution of electrical installation work [C1N-NRV]

As at 7 September 2026. In force. No commencement recorded.

Dates: made 22 May 2026; in force not recorded; ceased none recorded. Gazette: none recorded. Band B.

Synthetic. This instrument, its title, its number and its words are generated by the register, beneath the Act its recital names.

Cite: Circular CERC/CIR/2026/2968 of the Central Electricity Regulatory Commission dated 22nd May, 2026 on the execution of electrical installation work, Circular CERC/CIR/2026/2968, 22nd May, 2026 [C1N-NRV]. Machine: C1N-NRV.

CERC/CIR/2026/2968

Central Electricity Regulatory Commission

New Delhi, dated the 22nd May, 2026

CIRCULAR

To

All Chief Electrical Inspectors,

Subject: The execution of electrical installation work by electrical contractors under the Electricity Act, 2003, regarding.

In exercise of the powers conferred by section 9 of the Electricity Act, 2003 (36 of 2003), the Central Electricity Regulatory Commission hereby issues the following

1. References have been received seeking clarification on the manner in which section 9 applies to the execution of electrical installation work by electrical contractors.

2. The matter has been examined. Every electrical contractor carrying on the execution of electrical installation work shall make an application in Form III to the Authority within sixty days, accompanied by a fee of five hundred rupees.

3. It is, accordingly, clarified that a separate application shall be made in respect of each place at which the execution of electrical installation work is undertaken, and the Authority shall dispose of it within sixty days of its receipt.

4. Difficulties, if any, in the implementation of this circular may be brought to the notice of the Central Electricity Regulatory Commission.

(Chief General Manager)

Made under

Recital: "In exercise of the powers conferred by section 9 of the Electricity Act, 2003 (36 of 2003), the Central Electricity Regulatory Commission hereby issues the following". Names section 9 of the Electricity Act, 2003 (36 of 2003) [S21-JVE]. Vires verified.