Standing Order No. 4938/2015 of the Housing Department, Government of Gujarat dated 22nd October, 2015 on the execution of electrical installation work [C1C-YHP]

As at 7 September 2026. In force. No commencement recorded.

Dates: made 22 October 2015; in force not recorded; ceased none recorded. Gazette: none recorded. Band B.

Jurisdiction: Gujarat [IN-GJ]. Made by the Housing Department, Government of Gujarat.

Synthetic. This instrument, its title, its number and its words are generated by the register, beneath the Act its recital names.

Cite: Standing Order No. 4938/2015 of the Housing Department, Government of Gujarat dated 22nd October, 2015 on the execution of electrical installation work, Standing Order No. 4938/2015, 22nd October, 2015 [C1C-YHP]. Machine: C1C-YHP.

Standing Order No. 4938/2015

GOVERNMENT OF GUJARAT

Housing Department, Government of Gujarat

Gandhinagar, dated the 22nd October, 2015

STANDING ORDER

To

All Assessing Officers,

Subject: The execution of electrical installation work by electrical contractors under the Gujarat Electricity Industry (Reorganisation and Regulation) Act, 2003, regarding.

In exercise of the powers conferred by section 9 of the Gujarat Electricity Industry (Reorganisation and Regulation) Act, 2003 (Gujarat Act 24 of 2003), the Housing Department, Government of Gujarat hereby issues the following Standing Order for the guidance of all officers subordinate to it:

1. References have been received seeking clarification on the manner in which section 9 applies to the execution of electrical installation work by electrical contractors.

2. The matter has been examined. Every electrical contractor carrying on the execution of electrical installation work shall make an application in Form IV to the Petroleum and Natural Gas Regulatory Board within ninety days, accompanied by a fee of fifty thousand rupees.

3. The Assessing Officer shall ensure that energy bill is dealt with as directed above, and shall report compliance to the Petroleum and Natural Gas Regulatory Board within ninety days.

4. Difficulties, if any, in the implementation of this standing order may be brought to the notice of the Housing Department, Government of Gujarat.

(Secretary to Government)

Made under

Recital: "In exercise of the powers conferred by section 9 of the Gujarat Electricity Industry (Reorganisation and Regulation) Act, 2003 (Gujarat Act 24 of 2003), the Housing Department, Government of Gujarat hereby issues the following Standing Order for the guidance of all officers subordinate to it:". Names section 9 of the Gujarat Electricity Industry (Reorganisation and Regulation) Act, 2003 (Gujarat Act 24 of 2003) [S2K-Z8R]. Vires verified.