Circular of the Central Electricity Authority dated 12th September, 2007 on section 4 of the Petroleum and Natural Gas Regulatory Board Act, 2006 [C10-H6B]
As at 7 September 2026. In force from 12 September 2007.
F. No. 38/34/2007-CENT
Government of India
Ministry of Power
Central Electricity Authority
New Delhi, dated the 12th September, 2007
To
All Electricals Inspector and Appropriates Commission
Subject: Section 4 of the Petroleum and Natural Gas Regulatory Board Act, 2006 (19 of 2006), the distribution of electricity, regarding.
1. References have been received in the Central Electricity Authority seeking clarification on the manner in which section 4 of the Petroleum and Natural Gas Regulatory Board Act, 2006 (19 of 2006) (hereinafter referred to as the Act) is to be applied to distributions licensee who undertake the distribution of electricity at more than one place.
2. The matter has been examined. Section 4 of the Act requires every distribution licensee to make an application to the Central Commission within the period stated in that section.
3. It is, accordingly, clarified that a separate application shall be made in respect of each place at which the distribution of electricity is undertaken, and the Central Commission shall process each application in accordance with section 4 of the Act and the rules made thereunder.
4. Difficulties, if any, in the implementation of this circular may be brought to the notice of the Central Electricity Authority.
(Under Secretary to the Government of India)
Made under
No enabling provision stated.
Acts on (0)
none
Acted on by (0)
none
Not held (0)
none